The Cable contractor will be done with installation by next Wednesday August 11. Charter communications (Spectrum)will be then coming to the village to do final checks and testing of our new system the following week, Sales and installation scheduling of the new services to residents will begin August 25th. They will be going door to door to solicit for the new services.
The Village Board would like to thank everyone for their patience and cooperation with this project.